Our Work

  • Four undergrounds of new boulevard are furnished.
  • Floor 
  • walls 
  •  ceiling of the undergrounds 
They are furnished with innovative ceramic tiles with the size 3000x1000x3mm &3000x1000x5mm (Italy).

  • At first was done the installation of aluminum sub construction on walls and ceiling.
  • Based on the specification of the underground we have installed protective tiles of “Hekim Board” on the walls on which was laid ceramic tiles with “MAPEI” adhesives and sealants.
  • Historical pictures of the city was painted on ceramic tiles of the wall (Chemical process – Italian technology).